LPh 8 duties checklist: 16 basic services, four phases, one piece of evidence per duty

What the German fee ordinance HOAI requires in service phase 8 fits on half a page of Annex 10. What has to be provable when a dispute arises years later is written nowhere — this checklist closes that gap.

A working aid by Open Experience GmbH. Last updated: September 2026

What is the LPh 8 duties checklist?

The LPh 8 duties checklist maps the sixteen basic services of service phase 8 under the German HOAI (Annex 10.1, letters a to p) onto the four phases of a construction project — start of construction, ongoing execution, acceptance and the period after it. For every duty it names the concrete action, the evidence that must exist for it, and the rhythm in which the line falls due again. It is written for site supervisors, construction managers and client representatives who must not only perform their service but prove it in a dispute.

Legal framework: Germany (Civil Code BGB, construction contract rules VOB/B, fee schedule HOAI). Other countries have different rules, and contractual agreements take precedence over the standard periods named here.

Download the checklist

As a PDF to print and tick off, as a Word file to adapt to your own office. Content and structure are the same as on this page.

Last updated: September 8, 2026 · No form, no sign-up.

The checklist reflects German law (HOAI, VOB/B, BGB). In other jurisdictions it is a structuring aid, not a list of legal duties.

How to work with the checklist

  • Set it up once per projectEnter project, service phase and responsible person in the header. It is deliberately blank — a sample entry would add nothing here.
  • The evidence column is the coreIt is not the tick that counts but the document behind it. Where the evidence is missing, the duty has not been performed in a dispute — no matter how often you were on site.
  • Keep the rhythm"per working day", "per inspection", "once": the last column tells you when a line falls due again. Ticked once rarely means done.
  • Strike out instead of leaving blankNot every basic service arises in every project — letter b (structures with low planning requirements) and l (public-law acceptances) depend on the building. A struck-out line is a decision, an empty one an omission.

A tick without evidence is a claim. Evidence without a tick is still evidence.

Phase 1 — at the start of construction

One-off decisions that carry every later line. What is missing here cannot be made up later.

Duty (HOAI Annex 10.1)What to doEvidenceRhythm
a — Supervise executionCompile the basis for checking: permit with conditions, construction contracts, approved execution documents per trade, applicable regulations and recognised rules of technologyDrawing register with revision index and approval date; list of permit conditionsonce, updated with every drawing revision
b — Structures with low planning requirementsClarify which components of the structural analysis the site supervision itself checks for conformityNote of the components concerned; structural analysis on fileonce
c — Coordinate those involvedSet up the list of parties: client, specialist planners, contractors, authorities — with responsibility, deputy and contact detailsList of parties with date; distribution listonce, maintained continuously
d — Draw up the scheduleDraw up the schedule as a bar chart with milestones and dependencies between tradesSchedule with date and revision indexonce
e — Set up the site diaryDefine the documentation routine: who records what, with which tool, by when; define the daily report type and distribution listMinutes of the kick-off meeting recording the decisiononce
o — Prepare limitation periodsRecord per contract: contractual basis (VOB/B or BGB), agreed limitation period, securitiesList of limitation periods per trade, without start date for nowonce, completed at acceptance

Phase 2 — ongoing execution

The phase in which the evidence is created — or missing for good. Trades that require intensive supervision have their own lines, because case law demands more there than spot checks.

Duty (HOAI Annex 10.1)What to doEvidenceRhythm
a — Supervise executionInspections according to criticality: simple work by spot check, damage-prone work closely, up to being presentInspection record per visit: date, location, finding, photoper inspection
a — Waterproofing (basement, roof, wet rooms)Check connections, penetrations and layer build-up before they are coveredPhotos with date and location reference before closingper section, before covering
a — ReinforcementRelease position, diameter, spacing and concrete cover before concretingRelease photo and release note per concreting sectionper concreting section
a — Thermal insulationCheck build-up, joints, connections and vapour barrierPhoto documentation per component; delivery notes of the insulation materialsper component, before closing
a — ScreedCheck build-up height, edge strips, movement joints and readiness for coveringResidual moisture measurement record; release before flooring worksper construction section
a — Building services pipeworkCheck routes, gradients and tightness before shafts and stud walls are closedTightness test records; route photos before closingper run, before closing
b — Structures with low planning requirementsCompare execution of the components concerned with the structural analysisCheck note with photo per componentper component
c — Coordinate those involvedHold site meetings, issue orders and instructions in writing, clarify interfaces between tradesMeeting minutes with distribution list; orders with date and addresseeper meeting, per order
d — Update the scheduleRun the target-actual comparison, incorporate disruptions and hindrances, notify delayUpdated schedule with revision index; notices of hindrance under § 6 VOB/Bweekly, at every disruption
e — Keep the site diaryPer working day: weather, firms present with headcount, work performed, deliveries, hindrances, orders, special occurrencesDaily report with timestamp — written promptly, not reconstructedper working day
f — Joint measurementMeasure work jointly with the contractor before it is coveredMeasurement sheet, signed by both parties, datedper section of work, before covering
g — Check invoicesCheck interim invoices technically and arithmetically, reconcile with measurementsCheck note on the invoice with date and reason for every deductionper invoice
h — Compare check result with contract sumSet checked sums against contract sum and change ordersContract overview per trade with change-order statusper invoice
i — Control costsCheck the account of work against contract prices, report deviationsCost status with date and sourcemonthly
k — Identify defectsIdentify defects, document them with photo and location, notify the responsible party with a deadline, supervise rectification (§ 4 (7) VOB/B)Defect with photo, location, responsible party and deadline; proof of receipt of the notice; clearance reportcontinuously, per defect
m — Compile the documentationFile evidence continuously: test certificates, records, as-built drawings, photo documentationOrdered project file with indexcontinuously

Phase 3 — acceptance

The date on which burden of proof, risk and time limits change hands. Two lines are regularly forgotten: the reservations and the start of the limitation period.

Duty (HOAI Annex 10.1)What to doEvidenceRhythm
k — Organise acceptanceCheck readiness for acceptance, agree the date with all contracting parties, involve the specialists, give the client a recommendation on acceptanceRequest for acceptance; invitation; written acceptance recommendationper acceptance and partial acceptance
k — Identify defects at acceptanceJoint inspection; record every defect individually with location, photo and deadline; list outstanding work separatelyAcceptance record with defect list, signed by both partiesper acceptance
k — Declare reservationsExpressly reserve known defects and the contractual penalty (§ 12 (4) VOB/B, § 640 BGB)Reservation in the record, verbatimper acceptance
l — Public-law acceptancesApply for official acceptances and take part in them (building authority, fire protection, inspection experts)Applications; acceptance certificates; note of attendanceper acceptance, depending on the building
j — Determine costsDetermine costs according to DIN 276 and compare them with the cost calculationCost determination with dateonce after acceptance
o — List limitation periodsEnter acceptance date, start, end and contractual basis of the limitation period per tradeList of limitation periods, handed over to the clientper acceptance
m — Complete the documentationBring together as-built documents, test and acceptance certificates, maintenance instructions and photo documentationHandover index with acknowledgement of receiptonce
n — Hand over the buildingCarry out the handover with keys, briefings and documentsHandover record, signed by both partiesonce

Phase 4 — after acceptance

Four or five years in which the project team has long moved on. What is not on a list expires.

Duty (HOAI Annex 10.1)What to doEvidenceRhythm
p — Supervise defect rectificationTrack the deadlines of acceptance defects, check rectification, document the clearance, set a grace period when a deadline expiresDeadline overview per defect; clearance report with photo; grace-period letter with proof of receiptuntil the last defect is cleared
o — Monitor limitation periodsKeep the end of the period per trade in view, inspect before expiry, notify new defects in writing (extends the limitation period under § 13 (5) VOB/B)List of limitation periods with follow-up dates; defect notices with proof of receiptevery six months, at the latest six months before expiry
g, h, i — Final invoiceCheck the final invoice, compare it with contract sum and change orders, release securitiesCheck note on the final invoice; release of the securityonce
m — Close the fileKeep the project file complete and in order — at least until the end of the longest limitation period, longer because of possible secondary liabilityRetention note with end dateonce

The five pieces of evidence demanded first in a dispute

Site diary

Continuous, timestamped, not written afterwards — the first thing experts ask for.

Photos before closing

Waterproofing, reinforcement, insulation — what is covered is proven only by the picture.

Defect notice with proof of receipt

A deadline without proof of receipt is no deadline.

Acceptance record with reservations

Without an express reservation, known defects and the contractual penalty are lost.

List of limitation periods

The proof that basic service o was performed — and the insurance against warranty periods quietly running out.

How this happens on the side

Inspection, defect, daily report and photo in one system, with timestamp and location — the file grows while you work.

The checklist as an inspection template in Construction Checklists

In Construction Checklists, the quality assurance application, this list becomes a project inspection plan: one checklist per component, and for every item a result, a photo and a responsible person. Failed items become a defect in Construction Defects with one click, and the record is generated as a PDF — the evidence from the third column files itself.

See Construction Checklists

Frequently asked questions

Why 16 basic services — one often hears of eleven?

In Annex 10.1 the HOAI lists sixteen basic services for service phase 8, letters a to p. Eleven is a common summary in which, for instance, the invoice and cost duties are merged into one item. The checklist follows the legal text so that no duty falls through the cracks.

Does the checklist also apply to civil engineering works or outdoor facilities?

The phase logic and the evidence column carry over, the letters do not: they refer to the scope of services for buildings and interiors (Annex 10). Outdoor facilities, civil engineering works and traffic facilities have their own, similarly structured scopes of services in Annexes 11 to 13.

Does the checklist replace the site diary?

No. The site diary is itself one of the duties (letter e). The checklist says that and how often it must be kept — the evidence is the daily report.

Does the site supervisor have to be on site every day?

No. What is owed is supervision according to criticality: spot checks for routine craftsmanship, presence for damage-prone work. That is why waterproofing, reinforcement, insulation, screed and building services have their own lines in phase 2.

What happens if a basic service is not performed?

The client can reduce the fee. In the event of damage, the proof of proper supervision is also missing — with the risk of joint and several liability alongside the contractor.

May I adapt the file in my office and pass it on?

Yes, that is what the Word version is for. Please keep the source and the date when you pass it on — then the recipient knows what it is based on.

Work through the checklist — with a system instead of a binder.

45 minutes on your project: how the list becomes an inspection plan whose evidence files itself.